...
Info |
---|
Please note that the fields listed below only represent the minimum required configuration. You can still configure more Custom Fields to for any Screen associated with projects added to Agile Hive. |
...
On the Portfolio level we strongly recommend to use company-managed projects created from the Kanban template.
Agile Hive provides functionality to projects on the ART Portfolio level that can be mapped to a dedicated issue type:
Milestones
In order to utilize the full featureset Agile Hive provides for projects on Portfolio level, make sure to provide at least the fields listed below with dedicated Screens for each of the issue types:
Portfolio Epic / Enabler: User Business Value, RROE, Time Criticality, Job Size, WSJF Value
Milestone: Milestone Date
...
On the Large Solution level we strongly recommend to use company-managed projects created from the Kanban template.
Agile Hive provides functionality to projects on the Large Solution level that can be mapped to a dedicated issue type:
Risks
Objectives
Milestones
In order to utilize the full featureset Agile Hive provides for projects on Large Solution level, make sure to provide at least the fields listed below with dedicated Screens for each of the issue types:
Capability / Enabler: User Business Value, RROE, Time Criticality, Job Size, WSJF Value, Assigned PIs
Risk: Impact, Probability, Exposure, Residual Impact, Residual Probability, Residual Exposure, Assigned PIs
Objective: Uncommitted Objective, Assigned PIs
Milestone: Milestone Date
...
On the ART level we strongly recommend to use company-managed projects created from the Kanban template.
Agile Hive provides functionality to projects on the ART level that can be mapped to a dedicated issue type:
Risks
Objectives
Milestones
In order to utilize the full featureset Agile Hive provides for projects on ART level, make sure to provide at least the fields listed below with dedicated Screens for each of the issue types:
Feature / Enabler: PI Involvement, Assigned PIs, Owning Team, Teams Involved, Assigned Teams, User Business Value, RROE, Time Criticality, Job Size, WSJF Value
Risk: Impact, Probability, Exposure, Residual Impact, Residual Probability, Residual Exposure, Assigned PIs
Objective: Uncommitted Objective, Assigned PIs
Milestone: Milestone Date
...
On the Team level Agile Hive supports company-managed projects created from one of the following templates:
Scrum
Kanban
Agile Hive provides functionality to projects on the Team level that can be mapped to a dedicated issue type:
Risks
Objectives
Milestones
In order to utilize the full featureset Agile Hive provides for projects on Team level, make sure to provide at least the fields listed below with dedicated Screens for each of the issue types:
Story: Story Points, Sprint, PI Involvement, Assigned PIs
Risk: Impact, Probability, Exposure, Residual Impact, Residual Probability, Residual Exposure, Assigned PIs
Objective: Plan Business Value, Actual Business Value, Uncommitted Objective, Assigned PIs
Milestone: Milestone Date
Sub-Task: No specific requirements
...