Estimated Completion Date
Availability
Type: READONLY
SAFe® layers: TEAM ART LARGE SOLUTION
Work Types: All default work types
Description
Displays the estimated completion date of the work item, calculated via the Agile Hive Issue Hierarchy based on its child work items. The calculation varies by hierarchy level:
Team Level: Reflects the scheduled end date of the last planned sprint to which the work item is assigned.
Large Solution & ART Levels: Calculated directly from the field values of their child items and cascaded upward through the hierarchy.
Limitations
The calculation of this field will be aborted or incomplete if a work item has more than 50 children or sprints.